M-59


Project Highlights:

  • Project completed ahead of schedule
  • More than 120,000 tons of asphalt manufactured and placed
  • 3.5 inches of asphalt placed over the 4-mile stretch

What We Did


A two-course overlay of existing concrete, this 4-mile long project spanned M-59 from I-75 to Crooks Road, a heavily traveled commuter route. During the first phase, we discovered the concrete was in worse shape than anticipated, increasing the concrete patching and asphalt repair work almost tenfold.

Before placing the leveling course of asphalt, a substantial asphalt wedge course — up to 8 inches deep — was placed to bring the cross slopes and super elevated sections up to Michigan Department of Transportation standards. A total of 3.5 inches of asphalt was placed over the entire freeway. More than 120,000 tons of asphalt were manufactured at the Crooks Road Plant for this project.