Alpena Airport RW 1-19 Phase 2
Project Highlights:
- 34,000 SYDs of 6” Cement Treated Permeable Base
- 34,000 SYDs of 16” Runway/Taxiway PCC
- 3,000 SYDs of 8” Shoulder PCC
- 17,000 CYDs of PCC & 7,000 CYDs of Cement Treated Permeable Base
- Major Expansion for Alpena Combat Readiness Training Center with addition of 2,000 linear feet of runway pavement
- 2024 - Recognized by Michigan Concrete Association for Excellence in Paving Airports- Small Category