Project Highlights:

  • $55 Million FDOT Contract
  • Widened 2 to 6 lanes
  • 80,000 tons of asphalt

What We Did


  • $55 Million Dollar FDOT Contract
  • Reconstruct 5 Miles of one of the most dangerous roads in FL
  • Transform a 2 lane highway into 6  lanes
  • Create the first ever Continuous Flow Intersection (CFI) in the state.
  • Utilized Full GPS for the roadway construction, including subgrade, base, asphalt, and over 100,000 LF of curb and gutter placed without stakes.