US-41


Project Highlights:

  • $37,887,000 FDOT project
  • 45,000 tons HMA
  • 2016 DBIA Transportation Merit Award Winner
  • Quality in Construction Award, National Asphalt Pavement Association

What We Did


This Florida Department of Transportation (FDOT) District One Design-Build project transformed a two-lane rural roadway into a six-lane divided suburban highway. We designed and reconstructed 3.4 miles of US 41 (from SR 951 to Greenway Road). Due to the presence of near-surface limestone drainage, utility installations were designed to be shallow to limit excavation into rock layers and reduce the risk of penetration into the Upper Floridian Aquifer. A joint-use trench was established to address utility relocations for 14 AOs within the project limits.