Home      This Issue      
   
Volume 1 • Issue 2

A Community Effort

The Road to the Future

Building Long-Term Relationships

Roadway Work Zone Safety

Main Street, U.S.A.

Scheduling: The Key to Success

Good Neighbors

Evolution of Concrete Part II

Working Knowledge

Recycled Asphalt

A Community Effort

Restoring Greenfield Village

One of Henry Ford’s more famous quotes is “Coming together is a beginning, staying together is progress, and working together is success.” Those words are an apt description for the recent efforts by Michigan contractors and The Henry Ford to renovate Greenfield Village, a 90-acre outdoor museum in Dearborn, Michigan.

The village is part of a historical site founded by auto pioneer Henry Ford in 1929 and now managed by The Henry Ford. The site also includes the Henry Ford Museum, the refurbished Ford Motor Company Rouge auto plant, an IMAX theatre, the Benson Ford Research Center, and the Henry Ford Academy.

 

“Greenfield Village needed massive renovations,” explains Wendy Metros, Director of Media Relations at The Henry Ford.

“We had to restore the 75-year-old infrastructure, which was antiquated. We had sewer problems and electrical problems.”

Members of the Associated Underground Contractors (AUC), Michigan’s heavy construction association, along with Ajax, came together to donate their time, resources, and engineering expertise — at cost — to rebuild what has become known as “America’s Hometown.”

“We recognized the importance of Greenfield Village and its historical significance, and we wanted to be sure that the community at large was able to come and discover what America was like over the past 300 years,” says Clarence Jones, the Ajax Estimator on the project.

For Ajax, it was just another example of the company’s long tradition of helping in Michigan when the occasion arises.

According to Tim Hay, Ajax’s Construction Manager for the job, the company paved the village’s service drive and secondary roads, a main road outside the entrance, and a number of small parking lots.

“The service road was a little more than a mile long,” he says. “We milled off three inches of the old asphalt, and another contractor graded it and prepared it for paving. We then installed a leveling course, but we left the road like that so construction traffic could use it. Finally, at the end of the project, we installed a new four-inch asphalt covering.”

The two-mile main entry road required milling off the old asphalt, a leveling course, and four inches of new asphalt. The parking lots, suitable for parking approximately 300 vehicles each, were graded for proper drainage, leveled, and topped with three inches of asphalt.

 

As the new asphalt was put down, Ajax checked to make sure the density of mat was correct and the asphalt properly compacted. “It is a quality-control measure we do to make sure everything is right,” Hay says. “If you don’t get full compaction of the asphalt, it will deteriorate a lot quicker.”

All told, Ajax placed more than 14,000 tons of its 1100L, 20AA asphalt mix. The roads and parking lots at Greenfield Village won’t need repair again for at least 12 years.

Rapid Response Teams

Greenfield Village originally wanted construction to take place in stages over two or three years, but AUC proposed closing the village for a time and completing all the work at once. Accordingly, the village was shut in October 2002 and then re-opened when the restoration was finished by June 2003.

Most of Ajax’s work at Greenfield Village took place over six weeks in April and May 2003. Because as many as 12 other contractors were involved in the renovations, Ajax often had to juggle crews and equipment, waiting for the other necessary repairs on sewers, water lines, and electrical lines to be done before paving could begin. Hay spent many hours at the site, working with the other subcontractors, trying to anticipate just when his crews would be needed.

“Still, I’d be on day-three of another job, and I’d be called and told we were needed for two days at the village. I’d have to move my crews and equipment there, pave, then move them back to the original job,” he explains.

“We just had to be very flexible,” Jones adds. “But we made the commitment, and we lived up to it.”

An engineer, hired by the village, reviewed costs each day to make sure they were in line with the budget. “We worked with an inspector at the end of every day, reviewing how many hours we worked and what materials were used,” says Hay. “At the end of each week, we’d discuss equipment moves and any extra costs. It allowed the village to gauge just how much money it was spending.”

Ajax-Manufactured Asphalt

All the asphalt used at Greenfield Village was manufactured at the Ajax Inkster plant because of its proximity to the project.

“Asphalt is a time-sensitive material,” explains Jones. “It comes out of the plant at a certain temperature, and the further it’s trucked, the more heat you lose.” Having asphalt at the right temperature is critical because it makes it easier to compact. “You need the temperature up to get proper compactions because without proper compaction, the pavement deteriorates quicker,” Jones adds.

In fact, all the asphalt Ajax supplies to any job undergoes a series of internal quality checks to make sure it is properly mixed and at the right temperature before it leaves the plant. The company has nine asphalt plants in southeastern Michigan and can supply any project with the right asphalt quickly.

Contractor Wall of Fame

To show its appreciation to everyone who helped in the renovation, Greenfield Village erected a “Contractor Wall of Fame” just outside the main entrance. It features the names of all the companies and workers who contributed to the project. “When you go out there now, you can take your children up to the wall and show them your name and your company’s name and explain your involvement in this historic project,” says Jones.

Before it reopened to the public, Greenfield Village also staged a special night for contractors and their families to visit and see its attractions, which included riding in authentic Model Ts, visiting Thomas Edison’s laboratory and the Liberty Craftworks, and strolling the working farms and Railroad Junction.

“We were proud to be part of this project,” says Jones. “It was challenging because we had to juggle schedules, but in the end it was very satisfying.”

Published by QuestCorp Media Group, Inc.