|
Overcoming Obstacles with
Nonreinforced Concrete
The widening and repaving of U.S. 131
and construction of two interchanges
is the largest single contract awarded
by the Michigan Department of
Transportation (MDOT). “The biggest
challenge was the sheer size and magnitude
of the project, which is a major highway
in Grand Rapids,” notes Erick Kind,
Delivery Engineer for the Grand Rapids
Transportation Service Center, a division
of MDOT.
Valued at $140 million, the three-year
project involved the construction of 27
new bridges, interchange ramps, and 18
retaining walls, along with the moving
of 5.5 million cubic meters of dirt and
installation of electrical systems and
signage. More than 20 subcontractors
worked on the project.
A Substantial Task
Three primary contractors — Ajax Paving
Industries, Inc., C.A. Hull Co., Inc., and
Kamminga & Roodvoets, Inc. — formed
a triventure, an unusual arrangement
that worked extremely well, according
to Hugh Luedtke, Project Manager
at Ajax Paving. Because 131 is heavily traveled,
juggling construction with the
necessary lane closings and rerouting of
traffic on the roadway were the toughest
parts of the job.
Specifically, the improvements to 131
called for widening the section of highway
extending from 44th to 76th Streets from
four to six lanes, with a median dividing
the two sections of three lanes, and replacing
the old asphalt and concrete roadway
with new concrete.
Interchanges were built at 68th Street and
also where 131 crosses the new M-6 highway,
a 20-mile roadway along the south
side of Grand Rapids due to be completed
in 2005. The work on U.S. 131 and the
68th Street interchange was completed last
November, while the new M-6 interchange
is due to be finished June 1, 2004.
Ajax Paving’s primary responsibility was
reconstructing the concrete pavement on
U.S. 131, as well as all associated ramps
and interchanges and two miles of M-6.
C.A. Hull built the bridges and retaining
walls, and Kamminga & Roodvoets was
responsible for the embankment, underground,
and excavation.
“Because there were so many bridges
and other existing structures, the scheduling
of each event was crucial, since the
bridge contractor couldn’t do the work
on his own, but had to be tied to the dirt
contractor and to Ajax for the paving,”
says Luedtke.
Staging the Project
The project was divided into five stages
— the first two for the construction of
northbound 131, the third and fourth on
southbound 131, and the fifth on the
M-6 portion of the interchange. “Up
front we agreed to let Kamminga &
Roodvoets be the lead contractor, so we’d
have a central voice,” Luedtke adds.
Managing the lane closures and rerouting
of traffic on 131 was a key challenge,
considering that the road is a major artery
out of Grand Rapids and that each lane
closure cost the contractors $15,000 a
day. “Originally, the plan was to close one
lane in each direction through 2002 and
2003, but in 2002 we worked with the
contractor to widen the existing bridge so
that we could fit two lanes of southbound
traffic and one lane northbound,” says
Michael Guter, Project Engineer at URS
Corporation, which represents the MDOT.
The $15,000-a-day savings that resulted
from adding an extra lane of traffic
resulted with the contractors receiving
a $1.5 million bonus. (The lane closure
rental costs are figured into the contract,
so if the cost is less, as in this case, the
contractors get a rebate.)
Managing the traffic in the midst of
construction was difficult, notes Luedtke.
“With the lanes being narrow, measuring
only 11 feet wide, and much of the traffic
being tourist-oriented there were numerous accidents during the project,” Luedtke
says. It was an added hazard.
The contractors met with the MDOT
engineer at least once a week to discuss
progress on the schedule and the effect
of construction on traffic flow. Meetings
were held with local business owners to
address traffic concerns and ways in
which to direct the detours. Electronic
message boards on the freeway redirected
the traffic, and closings of ramps and lanes
were announced on local radio stations.
Overcoming Obstacles
Guter notes that there were some unexpected
delays and cost increases.
For example, project engineers became
concerned about the stability of the soils
at the south end of the job after close
examination, which led to a change in
the type of bridge foundations. Originally,
spread footings, which distribute the load
over a wider area, were planned, but
instead the contractor installed pile-supported
footings, which are rooted
deeper in the ground and supported by
the underlying soils.
Another change was the decision by the
MDOT to switch from asphalt to concrete
on the 68th Street interchange.
“The roadway is expected to get a great
deal of turning movements and concrete
is stronger, so we negotiated a new price
with Ajax,” says Guter.
In another instance, a change in plans led
to $234,000 in savings, which was split
between the contractor and MDOT.
Originally the design specs for 131 called
for reinforced concrete to be used for the
paving, but Ajax proposed to MDOT to
use nonreinforced concrete instead. Reinforced
concrete consists of two layers of
concrete sandwiching a layer of steel mesh,
which is poured and installed in a continuous
process while the concrete is still
wet. Joints are sawed into the pavement
at 27-foot intervals to control the cracks
that inevitably occur with concrete.
Nonreinforced Concrete
“In reality these reinforced pavements end
up with cracks between the saw-cut joints
and deteriorate quicker than they’re supposed
to,” says Luedtke. Nonreinforced
concrete lacks the steel mesh, but the sawcuts
are made in closer intervals — every
15 feet — which better protects against
random cracking.
Because of the superior performance,
quicker installation process, and lower
cost of nonreinforced concrete, all states
except Michigan have switched to its
use for the building of highways, according
to Luedtke. Because Michigan adheres
to the older standards and isn’t sure the
nonreinforced concrete will last as long,
Ajax agreed to a seven-year warranty on
the pavement. “Other jobs have been
performed with nonreinforced concrete,
and we feel strongly that it will last
longer,” says Luedtke.
Despite initial doubts, Guter notes that the
MDOT is moving to nonreinforced concrete
pavements 100 percent. State officials
find “it works better." The engineer said
that Ajax had also agreed, as part of its
warranty, to guarantee not only the materials
and workmanship as in other warranty
projects, but also the performance of the
concrete pavement for a seven-year period.
This is two years longer than most other
warranties. “If the subgrade was bad, reinforced
concrete would be a better material,
but the MDOT paid for a strong subpavement
underneath, so Ajax is confident the
nonreinforced will work,” Guter says.
Ajax also was able to pave the road more
efficiently through use of cutting-edge
equipment, Luedtke says. Normally, a
steel bar, called a dowel bar, is placed
beneath each saw-cut by hand. But in this
case, Ajax used two types of pavers — a
Gomaco 2800 and a CMI — which saved
time by automatically inserting the bars
as the roadway was paved.
“It’s more efficient, and the quality of bar
placement is higher,” says Luedtke. The
Gomaco paver was used to pave a 24-foot swath making up two lanes, while
the third lane and 16-foot ramps were
paved with the CMI paver. “We do not
pave any wider than 24 feet at one time,
because your ride quality suffers when
you do,” explains Luedtke.
Ajax received a 100-percent bonus on the
strength of the concrete, which was well
in excess of the design criteria, Luedtke
notes. At the end of 28 days two test
cylinders of concrete are broken and compared
with the strength specified in the
design. If the cylinders are consistently
above the design strength, the contractor
gets a bonus. In fact, Ajax’s concrete
achieved 5,875 pounds psi (per square
inch) of average strength, a 67-percent
increase over the 3,500-psi specified
strength in the design.
“Despite unexpected changes, the immensity
of the job, and lots of rainfall in the
last year of the project, leading to delays,
it happened on schedule and within budget,”
says Kind. “The work went smoothly,
and you couldn’t ask for a better group
of people,” Luedtke adds, referring to the
triventure. Even though each contractor is
used to working on their own, everyone
worked well together. The result is a greatly
improved highway and interchange that
will be appreciated by motorists for many
decades to come. |